American Lithium WKN: A2DWUX ISIN: CA0272592092 Kürzel: 5LA1 Forum: Aktien User: Chapuisat

0,638 EUR
-1,77 %-0,012
29. Nov, 23:00:16 Uhr, L&S Exchange
Kommentare 4.868
L
LongByNature, 01.02.2023 13:17 Uhr
2
Table 1 – TLC Project PEA Key Highlights Description Units Base Case Alternate Case LCE Selling Price $/tonne $20,000 $20,000 Life of Mine years 40 40 Processing Rate P1 / P21 ROM Mtpa 4.4 / 8.8 4.4 / 8.8 Average Throughput (LOM) tpa 8,112,415 8,112,415 LCEProduced (average LOM)1 tpa 38,157 38,157 LCE Production (steady state) tpa 24,000 24,000 P2 LCE Production (steady state) tpa 48,000 48,000 LCE Produced (total LOM)1 tonnes 1,462,913 1,462,913 Unit Operating Cost (OPEX) LOM2 $/LCE tonne 7,443 817 MgSO4 Produced (average LOM)1 tpa n/a 1,663,213 MgSO4 Selling Price $/tonne n/a 150 Gross Revenue incl. Power & MgSO4 Credits $ B 29.7 39.4 Capital Cost (CAPEX)3 P1 $ M 819 827 Capital Cost (CAPEX)3 LOM $ M 1,431 1,439 Sustaining Capital Costs (undiscounted) $ M 792 763 Project Economics Pre-tax: Net Present Value (NPV) (8%) U$ M 3,642 6,056 Internal Rate of Return (IRR) % 28.8 38.6 Initial Payback Period (undiscounted) years 3.6 3.6 Average Annual Cash Flow (LOM) $ M 435 684 Cumulative Cash Flow (undiscounted) $ M 16,147 25,860 After-tax:4 Net Present Value (NPV)8%) Post-Tax $ M 3,261 5,157 Internal Rate of Return (IRR) Post-Tax % 27.5 36.0 Payback Period (undiscounted) years 3.8 3.7 Average Annual Cash Flow (LOM) $ M 396 591 Cumulative Cash Flow (undiscounted) $ M 14,617 22,219 Notes: Production: base case is 2 phases, 4.4Mtpa and 8.8Mtpa throughput; alternative case is identical, but with production of magnesium sulfate co-product over life of operations. Includes all operating expenditures with credit for excess power and revenue from MgSO4 production as offset to Unit LCE Opex, the estimate is expected to fall within an accuracy level of ±30%. Includes 10% contingency on process plant capital costs, 10% contingency is included in the tailings and infrastructure costs, and closure costs (LOM). Tax calculation estimates were completed by Mining Tax Plan LLP, and include Federal Taxes, all Nevada State taxes and royalties and Nye County Property tax estimates, and available producer tax credits.
L
LongByNature, 01.02.2023 13:17 Uhr
2
Mine Life & Production Simple truck and shovel open pit mining of the shallow resource underpins the scalable, long-life, lithium project producing approximately 24,000 tpa LCE over Years 1-6 expanding to 48,000 tpa LCE production for Years 7-19 years when mining ceases. Rehandling of the >1,000 parts per million (“ppm”) stockpile allows production to continue for Years 20-40. Average LOM Production of approximately 38,000 tpa LCE for 40 years. Targeted 1,400 ppm Li average feed grade pit-constrained resource supports mining for 19 years and processing >1,000 ppm Li stockpile for an additional 21 years. 1,400 ppm feed material beneficiation increases the head grade to leaching to 2,000 ppm Li. LOM Strip Ratio (Waste:Ore) of 0.93:1 with a maximum final pit depth of ~325-350’, well above the water table depth. Where possible progressive reclamation of mining areas is planned along with in-pit back-filling of waste rock and filtered tailings. Sulfuric acid leaching using industry standard techniques and flowsheet produces high purity lithium carbonate to enable the production of battery grade LCE or LiOH. PEA study estimates that for an additional $100M (Installed) Capex, and $406/t LCE Opex, a final conversion and refining processing step will enable the production of battery grade LiOH; or End users have the flexibility of acquiring high purity LCE from TLC and converting it themselves to whichever product is required. Magnesium sulphate (monohydrate) is an increasingly important fertilizer add-on product with a large and growing global market. High-purity hydrated products (heptahydrate & epsom salts) are used in the food, personal care and water quality industries.
L
LongByNature, 01.02.2023 13:16 Uhr
2
Simon Clarke, CEO of American Lithium states, “We are extremely pleased to announce a very robust maiden PEA for TLC. Our team has worked hard and spent considerable time getting an in-depth understanding of TLC mineralization and the best way to recover high purity lithium utilizing conventional processing methods with the latest techniques and best in class plant and equipment. A significant portion of the processing work has been done to pre-feasibility levels as we believe this will help us move quickly through the next phases of development. At 99.4% LCE purity, TLC offers the capability to produce either battery grade lithium carbonate or hydroxide with minimal additional refining. In this PEA, we showcase a long mine-life utilizing only the highest-grade sections of the deposit, with the potential for additional production ramp-up and mine life utilizing our mid-grade and lower grade sections. Not only are the economics very strong for high purity lithium production, but TLC also has the potential to produce high purity magnesium sulfates as by-products for agriculture and other end uses. As shown in the PEA, even assuming conservative pricing, these by-products can add significant economic value. At the same time, we have focused our work on ensuring we continue to minimize environmental impacts and water usage in the mining, processing and production of lithium from TLC.” TLC PEA Highlights (Alternate Case – Ramp-Up Production Li + Magnesium Sulfate production): Identical LCE production scenario, but with added LOM average production of 1,681,856 tpa of magnesium sulfate (“MgSO4” - monohydrate and heptahydrate) by-products; Pre-tax Net Present Value (“NPV”)8% $6.06 billion at $20,000/t LCE & $150/t MgSO4; After-tax NPV8% $5.16 billion at $20,000/t LCE & $150/t MgSO4; Pre-tax Internal Rate of Return (“IRR”) of 38.6% After-tax IRR of 36.0% Pre-tax initial capital payback period 3.5 years; after-tax payback 3.7 years Average LOM pre-tax annual cash flow: $684 million; annual after tax cash flow: $ 591 million Initial Capital Costs (“Capex”) estimated at $827 million Total Capex estimated at $1439 million; Sustaining Capital estimated at $763 million Operating cost (“Opex”) estimated at $7443/t LCE inclusive of power credits Operating cost (“Opex”) estimated at $817/t LCE, inclusive of power & MgSO4 credits PEA mine plan produces 1.46 Mt LCE and 64.9 Mt MgSO4 LOM over 40 years
x
xRapiDx, 01.02.2023 13:16 Uhr
0
So wie versprochen
x
xRapiDx, 01.02.2023 13:16 Uhr
0
Ja man!
L
LongByNature, 01.02.2023 13:16 Uhr
2
American Lithium Announces Positive Preliminary Economic Assessment for TLC, Base Case – After-tax NPV8% US$3.26 Billion & After-tax IRR of 27.5% VANCOUVER, BRITISH COLUMBIA, February 1, 2023 – American Lithium Corp. (“American Lithium” or the “Company”) (TSX-V:LI | NASDAQ:AMLI | Frankfurt:5LA1) is pleased to announce the results of its maiden Preliminary Economic Assessment (“PEA”) for the Tonopah Lithium Claims (“TLC”) project located in the Esmerelda lithium district northwest of Tonopah, Nevada. This independent PEA was completed jointly by DRA Global and Stantec Consulting Ltd. (“Stantec”) and demonstrates that the TLC project has the potential to become a substantial, long-life producer of low-cost lithium carbonate (“LCE” or “Li2CO3”) with the potential to produce either battery grade LCE or lithium hydroxide (“LiOH”). The PEA base case envisions an initial 4.4 Million tonnes per annum (“Mtpa”) processing throughput expanding to 8.8Mtpa. The PEA alternative case is identical, but with added production of high purity magnesium sulfate as a by-product over life of operations. Unless otherwise stated, all dollar figures are in US currency. TLC PEA Highlights (Base Case – Ramp-up Production Li only production): Pre-tax Net Present Value (“NPV”)8% $3.64 billion at $20,000/tonne (“t”) LCE After-tax NPV8% $3.26 billion at $20,000/t LCE Pre-tax Internal Rate of Return (“IRR”) of 28.8% After-tax IRR of 27.5% PEA mine and processing plan produces 1.46 Mt LCE LOM over 40 years Pre-tax initial capital payback period 3.6 years; after-tax payback 3.8 years Average LOM annual pre-tax cash flow: $435 million; annual after tax cash flow: $ 396 million Initial Capital Costs (“Capex”) estimated at $819 million Total Capex estimated at $1,431 million; Sustaining Capital estimated at $792 million Operating cost (“Opex”) estimated at $7443/t LCE inclusive of power credits
p
pfeiffer3383, 01.02.2023 13:16 Uhr
0
PEA gerade gekommen
DonauPirat
DonauPirat, 01.02.2023 11:47 Uhr
1

Post wurde gelöscht.

Da das PEA und der Quartalsbericht wahrscheinlich erst nachbörslich veröffentlicht werden müssen wir wahrscheinlich noch bis morgen warten
Mehr zu diesem Wert
Thema
1 AMERICAN LITHIUM Hauptdiskussion
2 American Lithium News only
3 American Lithium
Meistdiskutiert
Thema
1 MEITUAN DIANPING Hauptdiskussion -12,73 %
2 IonQ +14,00 %
3 Reconnaissance Energy Africa Hauptdiskussion -6,82 %
4 Media and Games Invest -1,73 %
5 BIGG Digital Assets Hauptdiskussion +1,21 %
6 Aker Carbon Capture +8,65 %
7 GAMESTOP Hauptdiskussion -6,08 %
8 STATOIL ASA Hauptdiskussion -0,18 %
9 Novavax Hauptdiskussion +1,34 %
10 FORMYCON Hauptdiskussion +0,40 %
Alle Diskussionen
Aktien
Thema
1 MEITUAN DIANPING Hauptdiskussion -12,73 %
2 IonQ +14,00 %
3 Reconnaissance Energy Africa Hauptdiskussion -6,82 %
4 Media and Games Invest -1,73 %
5 BIGG Digital Assets Hauptdiskussion +1,21 %
6 Aker Carbon Capture +8,65 %
7 GAMESTOP Hauptdiskussion -6,08 %
8 STATOIL ASA Hauptdiskussion -0,18 %
9 Novavax Hauptdiskussion +1,34 %
10 FORMYCON Hauptdiskussion +0,40 %
Alle Diskussionen